1.No-load start
The hydraulic cone must be started under no-load condition. After the crusher is in normal operation, the mine can be started to avoid the increase of the motor load, resulting in excessive starting current and even burning the motor.
2. The amount of feed should be even
Timely adjustment of the amount of ore to be added, to ensure that the amount of minerals is evenly and properly added, so as not to increase the local friction of the machine, so that it appears "card machine" phenomenon.
3. Pay attention to check the running part
The hydraulic cone is broken in the * trial operation stage after installation. It should * check whether the running part has stuck or collided. After the inspection is normal, the operation can be started. When running, * run the load for 4 hours, check the flexibility of the pulley, whether the machine is installed firmly, and whether there are other noises.
4. Pay attention to the temperature rise of the rotor main bearing
When the machine is running, pay attention to observe the temperature rise of the main bearing of the rotor. If the temperature rises above the specified value, it should be sped and checked quickly. During operation, if the machine vibrates too much or an abnormal sound occurs, s it quickly and check the cause.
5. Repair and replace worn parts in time